ANIL MINCONMINING · INFRA
Request a quote
Benched hard-rock cut on a forested hillside alignmentPlaceholder · replace with site photo
2023–25 · Vizianagaram, Andhra Pradesh

Raipur–Visakhapatnam Expressway · RVAP-1

For H.G. Infra Engineering Ltd.

98,814 m³Rock Excavated
Zero LTISafety Record
₹6.50 CrContract value
2023–25Duration
The brief
Client · H.G. Infra Engineering Ltd.
Location · Vizianagaram, Andhra Pradesh
Years · 2023–25

Hard-rock excavation via controlled drilling & blasting, including breaking, loading and disposal to designated leads.

Delivered fully on schedule with a Zero Lost-Time-Injury record — repeat-engagement partner status confirmed with H.G. Infra Engineering Ltd.

Client quoteAdd a named quote or appreciation letter from H.G. Infra Engineering Ltd. here, with written permission.
Benched hard-rock cut on a forested hillside alignment
01

Before

A forested hard-rock alignment in Vizianagaram, with live construction traffic on the corridor.

Haul trucks lined up on a mine floor under a clear sky
02

Drill

Crawler drills on a designed pattern. Every hole logged.

Controlled blast throwing rock and dust on a hard-rock bench
03

Blast

Certified blasters, controlled charges, vibration monitored on every shot.

Backhoe loader with bucket raised on site
04

Haul

Breaking, loading and disposal to designated leads, reported daily.

Site crew member in hard hat and high-visibility vest
05

Handover

98,814 m³ moved. On schedule. Zero lost-time injuries.

Got rock to move? Let’s talk.

An engineer replies within 48 hours.

Request a quote
Call WhatsApp